Scheduled Dedicated Server Migration - August 16
« on: August 16, 2012, 05:55:54 PM »
The migration of servers scheduled to move tonight is beginning.

Offline ShojiH

  • Galactic Royalty
  • *****
  • Posts: 215
Re: Scheduled Dedicated Server Migration - August 16
« Reply #1 on: August 16, 2012, 06:38:32 PM »
Servers have left San Diego and are on their way to Irvine.

Offline ShojiH

  • Galactic Royalty
  • *****
  • Posts: 215
Re: Scheduled Dedicated Server Migration - August 16
« Reply #2 on: August 16, 2012, 08:20:54 PM »
Servers have arrived in Irvine and are being racked and plugged in now.

Offline ShojiH

  • Galactic Royalty
  • *****
  • Posts: 215
Re: Scheduled Dedicated Server Migration - August 16
« Reply #3 on: August 16, 2012, 08:47:48 PM »
All servers are plugged in now we are currently checking to verify all servers are back up and working.

Offline ShojiH

  • Galactic Royalty
  • *****
  • Posts: 215
Re: Scheduled Dedicated Server Migration - August 16
« Reply #4 on: August 16, 2012, 09:05:36 PM »
All servers are back online in Irvine.  Please contact support if you have any issues.

 